Magnolia Avenue construction, phase by phase

Cast iron water mains and alley sewer lines are being replaced under Magnolia Avenue and nearby Near Southside streets, spring 2027 to spring 2029. Pick a month or a phase to see which blocks are affected.

Timeline

May 2027
Apr 2027Jan 2028Jan 2029

Phases

    What to expect on your block

    • Work hours: 7 a.m. to 6 p.m. weekdays; some Saturdays 9 a.m. to 4 or 5 p.m. with city approval.
    • Notice: 48-hour alert to businesses; door hangers 7 days and 1 day ahead.
    • Water service: two planned shutoffs of 15 to 30 minutes each.
    • Traffic: lane closures with flaggers; the contractor sets final phasing.
    • Emergencies: 817-392-4477, option 1.
    • City project manager: Clayton Torrance, 817-392-8528.

    Important: start months assume a May 2027 start. Completion months are the city's targets tied to Open Streets (April 2028) and ArtsGoggle (October 2028), not committed end dates. Dashed sewer lines show approximate alley positions.

    Sources: City of Fort Worth pre-construction presentation, City project page, Fort Worth Report. Street geometry © OpenStreetMap contributors.